Wednesday, December 18, 2019
THERE'S LIGHT AT THE END OF OLD PORT ISABEL ROAD BRIDGE
By Juan Montoya
According to notices passed out to Cameron County Public Works crews, Rene Capistran's Noble Texas Builders was supposed to start work on repairing the damaged Old Port Isabel Road Bridge over the eastern segment of the Resaca del Rancho Viejo October 7.
But given the normal delays associated with county bureaucracy, it wasn't until one month later, on November 7, that the contractor posted this sign below informing the public that it would start work then.
Before that, Public Works crews started the prep work for the construction of the new bridge over Old port Isabel Road in commissioner Joey Lopez's Precinct 2.
Workers were at the site clearing brush and vegetation from the right-of-way and cleared some trees with their backhoes. The start of the project was delayed a bit longer since a fiber optic cable runs under it and had to be rerouted before work could proceed.
The bridge was closed in mid-2019 after is sustained extensive guardrail damage that made crossing it dangerous to the public.
The thoroughfare is used by many of the neighborhoods in the area and is used to go from FM 802 to FM 511. When the bridge was closed it forced local residents and motorists heading north to use an alternate route around the Buena Vista Cemetery and then on to FM 511.
According to the announcement the work was supposed to take 10 weeks, weather permitting. Noble Builders was granted the $285,000 contract without bids after the county commission declared it an emergency acquisition.
Now, as the end of the year approaches, instead of Dec. 14 the 10 weeks after Nov. 7 will be mid-January 2020 before motorists and residents living there will have access to the bridge. However, all hope is not lost. The concrete box culverts are in place and the rest of the work –guardrails, signage, asphalt overlay, etc. – are the only thing left to construct once the culvert is declared set.
There is light at the end of the bridge.
Subscribe to:
Post Comments (Atom)
9 comments:
juan ya mero, remember these city and county projects when done in house usually take 3 or 4 times more time and money then when bidded out. you know how it works.
The city took one year to repave Roosevelt st (two blocks), the county wil take a half decade to rebuild the bridge. Why? The city engineers from the city went to the county. They now want to install placic curbs all over the county.
what happened to a bridge? the bridge would allow for row boat crossing and other small non power boats.
awly costly for a culvert
Looks like they're gonna install several plastic curbs.
God & Governing: State Rep. Eddie Lucio III and sen. EDDIE LUCIO jr.God & Governing: Hear from two Texas officials on how their faith guides their policymaking, from abortion and same-sex marriage.
All bridges over resacas need to be enlarged. These short little bridges restrict the flow of water creating silting. Save our resacas
Kinda late to say that even with timing, we have a bunch of morons at the county and the city and that's not saying much for the port and pub less not forget BISD. Coming from austin to brownsville you can smell the rancid in the air as you get close you feel like turning back...no shit
They have lefter over 6 inch pipes from the project to stop the flooding at boca chica and now they are replacing the bridge with a 6 inch pipe que pendejos...
Merry Xmas maggots and a Happy New Year
Post a Comment